NORWALK, Conn. – After a year of intensive study, Charlie Taney has a good understanding of the issues surrounding Manresa Island and is pessimistic as to its outcome, he said. But he and the Manresa Association have an idea for a proactive step, and are trying to convince Norwalk to spend money on it.
The Connecticut Center for Economic Analysis, part of the University of Connecticut’s School of Business, is “really excited” about doing a study of likely economic impacts of potential developments of the island, where the now-closed power plant looms over Norwalk, because it’s the type of study that would have an impact on a community, Taney said. Mayor Harry Rilling is interested in the idea but skeptical of spending money in the upcoming budget for the “significant” expense, Taney said.
Rilling did not respond to a request for comment.
Taney shared all of this information at a recent meeting of the Coalition of Norwalk Neighborhood Associations (CNNA), where he gave an update of the first year of the Manresa Neighborhoods Association (MNA) in an effort to recruit more community interest.
He said he and another association member spent an entire day in Hartford, wading through stacks of documents that covered two conference room-sized tables, studying records about the island and its environmental contamination. The property, which has been owned by NRG Energy for 12 years, has a 1- to 2-foot layer of coal ash about 5 to 10 feet deep on 55 of its 125 acres, he said. There doesn’t appear to be any contamination in the sound but there are some issues in the four freshwater wetlands on the property, he said.
The Connecticut Department of Energy and Environmental Protection (DEEP) has not given NRG any guidance as to what level of remediation would be acceptable because that would be determined by the intended use for the property, Taney said. NRG has laid out three or four options and is “actively trying to sell the island,” he said.
“That’s going to be a long process, that’s going to take probably years to figure it out,” Taney said. “There’s no guarantee that it will ever be sold because I’d say there’s a reasonably good chance it’s going to be a stalemate.”
NRG won’t repower the plant because it makes no economic sense, he said.
“They can’t find anybody to buy it because they can’t find anybody who can figure out how to buy this property, take the plant down, clean it up and then make money. That might not be possible. Five years from now we could have a situation where it’s just like the plant is sitting there, it’s mothballed as it is now, the staff comes and goes, but it’s mothballed,” Taney said. “So five years from now you could have a situation where they’d like to sell it but no one wants to buy it.”
His account of NRG’s intentions are confirmed in a letter the company sent to state Sen. Bob Duff (D-25).
Senator Duff update letter 10-9-14 final NRG
“We have evaluated power generation options and technology and spent considerable months on the analysis this year,” NRG Vice President for Governmental Affairs Ray Long wrote in October. “At this time, we do not see any viable options, as the market does not support the significant cost of either building a new facility at Norwalk Harbor or using the existing site and facility for a new power project.”
Long mentioned that NRG is seeking a lower tax assessment because the plant is no longer operating and outlined the process that NRG would likely use to redevelop the site:
- Hire a real estate advisor with development expertise (i.e., not just a broker)
- Perform real estate assessment;
- Select a developer based on knowledge gained from the real estate assessment;
- Entitle/subdivide the property in accordance with its identified highest and best use;
- Prepare the site for development including any applicable remediation and demolition;
- Construct horizontal infrastructure;
- Construct vertical infrastructure; and
- Market the property.
“As you can appreciate, the redevelopment process will be lengthy and capital intensive and we are evaluating whether we can develop a business case for this approach,” Long wrote.
There are no buyers, he wrote at the time.
“Five years from now we may have a situation where we have to get the feds and the state to try to step in and broker a solution,” Taney said.
An economic impact analysis done now would arm the city with information should an option for development arise, he said. It would take 12 to 18 months to do, after a Request for Proposals (RFP) process that could take up to six months, and, if the city agreed to fund half the expense, the Manresa Association would raise the other half he said, declining to say how much money it would be. If the city isn’t in, then potential funders would say that the chief beneficiary wasn’t interested.
The study would narrow down the range to four potential options for the property, he said. His choices would be:
- Nothing happens.
- It’s made into a wildlife refuge
- It’s developed to the maximum extent allowed. As it is zoned residential, that would likely be condominiums and a marina
- It’s developed to half of what it could be approved for
It could become part of the Stuart McKinney Wildlife Refuge, he said.
“You could say, ‘Let’s have the feds take over. There would be no liability for Norwalk,” he said.
The association has an appointment with NRG to see if the company has any interesting in helping to fund a study, he said.
The Manresa Neighborhoods Association went from knowing “zero about the property to now having a pretty good handle on what’s going on out there,” he said. It would like to have a more diverse group of people involved, including the South Norwalk residents who also live in close proximity to the closed power plant, he said. The association should have a website online by mid-January and is planning an event to mark the two year anniversary of the plant’s closing in June, he said. It also plans to educate political candidates on the issue and then ask them to take a position, he said.
MNA has done well, he said. “We feel pretty good that we set our objections, recruited seven associations, attracted support from eight partners, identified the contamination and developed an economic impact analysis proposal in our first year,” Taney said.