The Norwalk Planning and Zoning Commission got its first look at plans for a 12-story, mixed-use building with 266 apartments, a town square, and a dog park across from the Merritt 7 train station on Glover Avenue.
While the commission opened the public hearing, it did not vote on the plans on Wednesday evening as it was still waiting for a report from the project’s peer review architect.
Three members of the public spoke, mainly questioning the potential impact of traffic from the development.
“What is the impact going to be when all of the buildings are done?” asked resident Brett Carey, who lives off of Oakwood Avenue near the project. “Right now, traffic coming down, especially with that extra garage entrance coming down Oakwood, I believe that will create significant traffic, so just wondering what the traffic impact will be with all the buildings.”
Resident Joanne Horvath reminded the commission of the proposed Route 7–15 project that will cause more construction and traffic-related issues in the area.
“If BLT plans to build a 12-story apartment complex at the south end of Glover Avenue, this is going to add more congestion to this already overburdened traffic area,” she said. “And this is not counting the additional projects that are going up in the area.”
Resident Joann Ciavarelli raised concerns about the intersection of Glover and Grist Mill, which can be crowded.
“It’s a long light and inevitably people are running red lights like crazy at certain times of the day,” she said. “That connector gets backed up and it’s a bottleneck—there’s nowhere to go. I can’t imagine with another 200-plus cars what the impact is going to be.”

A Look at the Changes
The proposed development is part of an approved North Seven master plan that calls for more than 1,200 new apartments across seven buildings, along with retail space and additional amenities, such as a park.
However, the plans for Phase 1 have been updated, David Waters, the attorney for the developer Building and Land Technology, explained.
What had been two separate buildings on the master plan—1.1 and 1.2—the updated proposal combines them into one building that ranges from five to 12 stories, with 266 residential units, along with an accessory retail building, a dog park, and a town square. The building also includes some amenities for its residents, such as a swimming pool.
The number of units has decreased slightly from 273, and the amount of retail space in this phase has also been reduced from 17,166 to 8,492.
Waters said combining the buildings allowed for more space for the town square and the addition of the dog park. Phase 1 now has a total of 18,000 square feet overall in the town square area.
“And in addition to that, we now have an additional green space that did not exist because it’s where building 1.2 was located. And that’s approximately 23,000 square feet of new green space,” he said.
Waters said that they decided to add a dog park because they’d seen how popular pets are in their developments in Stamford and at the Curb in Norwalk, which is farther up the road on Glover.
“The pet population is almost as big as the human population,” he said. “It’s pretty astounding.”
The planned retail space would aim to be a complement to the area, he said.
“The pavilion building has retail space in it very much contemplated to be a coffee shop type destination, particularly for people that are either at the dog park or that are commuters,” he said, adding that there would also be bathrooms.
The plans also include 35% of green roofs for the building, and Waters noted that they’re using the same brick pavers and patterns that the state used in its redo of the Merritt 7 train station so the street looks consistent.
“The green roofs that are down here create interest, they create cooling effects,” he said. “They’re part of what you’ve recognized as what you wish to have on these buildings. And so we have proposed them in an area where people can actually see them.”

Some Remaining Questions
When the master plan was approved, some conditions were placed on the developer that Waters said are in the process of being met—mostly due to circumstances beyond their control.
For example, the developer was required to apply to the state Department of Transportation to add a sidewalk that would stretch from the intersection of Glover Avenue and Grist Mill Road down to Main Avenue.
“We did, in fact, as required, make that application last July to DOT,” he said. “TMP was copied at the time that we did it and is well-aware that that application was made. DOT at this point has not given a yay or nay on whether they would allow that to be done at this time.”
The City’s Transportation, Mobility, and Parking Department also asked the builders to consider adding a sidewalk from Oakwood up Glover, toward the One Glover apartment complex.
“We don’t disagree at all. But we have no ability to provide for it because there aren’t sufficient rights within the right of way to be able to install it—It requires the acquisition of rights from private property owners that aren’t us,” he said.
The solution Waters proposed is that if the city “can acquire the rights that are necessary to install a sidewalk in that location, we will install that sidewalk within a year after those rights are provided to us.” That means they’d paid the cost of the sidewalk construction, but not the acquisition of property.
While the members of the public questioned the amount of traffic the proposed building was going to bring, the applicant’s traffic engineer, Mark Vertucci, said that the site had “excellent access” to main roads, such as Route 7 and the Merritt Parkway, and “excellent transit access with the Metro North station right across the street.”
“The findings of our study, the proposed residential development will not have a significant impact to the traffic operations in the immediate study area,” he said.
Next Steps
The plan is for the applicant to come back before the commission, ideally at its March 6 meeting, with the comments from the peer-review architect. Members of the public can also continue to comment at that time.











Leave a Reply