Correction, 4 a.m., March 27: Cars would take right hand turn from southern driveway, turn around in parking garage.
NORWALK, Conn. – Three letters are key to the defense of traffic studies that say a big box store will work on Main Avenue: D-O-T.
Traffic engineer Michael Galante used those letters over and over again Wednesday in responding to traffic allegations made on behalf of the Norwalk Association of Silvermine Homeowners (NASH) as a key point of their fight against The Village, a big box store development planned for the Superfund site at 272-280 Main Ave.
Not only is the Connecticut Department of Transportation (ConnDOT) is in agreement with the work done by Galante’s firm, but the traffic analysis done on behalf of NASH was hurried and used inaccurate assumptions and old information, Galante said at Wednesday’s Zoning Commission public hearing.
Zoning Commissioners went on to ask a series of questions designed to address the public’s concerns, and then sent the application back to Committee.
Joe Fishinger of NV5, hired by the Commission to do a peer review of Galante’s work, continued to agree with Galante that the timing of the Main Avenue lights would mitigate the development’s traffic.
This last phase of the public hearing on the proposal was generated by traffic studies presented by NASH on March 15, during a hearing continued from March 1 just for the purpose of discussing traffic implications.
There’s no tenant announced for the big box store; opponents widely suspect it will be a BJ’s Wholesale Club because that was what was proposed for the site in 2013.
Attorney Liz Suchy began the rebuttal of the NASH traffic analysis, first saying that comments from the public damning the unknown nature of the big box store were not valid, as Zoning approves retail all the time without knowing who the tenant will be.
As an example, the Waypointe development on West Avenue has storefronts but no tenants were lined up when it was approved, she said.
While David Spear of DLS Traffic Engineering, a Hartford firm, said on March 15 that a WB67 tractor trailer would not be able to handle the driveway planned for The Village, Suchy said Galante’s design was precisely designed for that size truck.
DLS and Adler Consulting, NASH’s other traffic expert, used Galante’s August plans instead of his updated ones, she said.
Galante said his firm, Frederick P. Clarke Associates, has been studying Main Avenue for four years while the NASH consultants have looked at it for weeks.
ConnDOT and the Office of State Traffic Administration (OSTA) review the traffic plans for the project, as Main Avenue is a state road, he said.
“We have had discussions with DOT during that process,” Galante said. “I think they are in general agreement with everything that we have done.”
“DOT has reviewed and approved” the scope of the study, and “DOT has reviewed and approved” the traffic volumes, Galante said.

Opponents “disagree with that data but I don’t believe they talked to DOT,” he said. “…Everything we have done to analyze and include that in our model, DOT agrees with. So the way we approached it, they have been a part of that discussion and they agree with it. Eventually we will have everything in writing from DOT.”
The state shares its accident information with the traffic engineers but traffic engineers are not permitted to make that data public due to liability concerns, Galante said.
“I would guess (the NASH consultants) spent seven to 10 days looking at the documents,” and “I would guess they haven’t talked to city staff or NV5,” Galante said.
If another type of development were allowed to go onto the site you’d wind up with five or six driveways without the traffic mitigation plans that The Village can afford to implement, plans that will have state approval, he said.
That includes widening Main Avenue in front of the project, which The Village can do because it’s all one property and the applicant is willing to give the needed land to the state, Galante said.
The process with the state will continue for nine to 10 months, he said.
“We will not get a permit from OSTA or a permit from DOT unless we satisfy all of their conditions,” Galante said.
Zoning Commission Vice Chairman Lou Schulman asked if OSTA would allow public input as it reviews the traffic proposals.
No; the Department of Public Works will have input on behalf of the citizens, Galante said.
“Can the neighbors be assured that OSTA’s concerns mirror theirs?” Schulman asked, mentioning fears that drivers will leave Main Avenue and travel through neighborhoods.
“We don’t want traffic to divert to a local street,” Galante said. “That is a statement that, quite frankly, we are very serious about.”
Not only is the state process a year long but, “if there is something a year from now that didn’t work out the way we said it would we are obligated to fix it,” Galante said.
Another issue brought up on March 15 was the mountable curb planned for the right hand turn only driveway at the development’s southern end. That’s so emergency vehicles can go over it, Galante said.
“It is designed to accommodate the (largest) tractor trailer,” Galante said. “… The truck, unless he is a terrible driver maybe, he will not go over that mountable curb, that raised median.”
Schulman asked if an island could be installed in the middle of Main Avenue to keep drivers from turning left.
“I would doubt it because of the hazard of hitting it,” Galante said.
Commissioner Roderick Johnson asked about the developments planned for Glover Avenue.
The amount of traffic that will leave those apartment buildings and head for Main Avenue is actually very small, as drivers are expected to head for the Merritt Parkway or Glover Avenue and the Route 7 connector, Galante said.
“Our impact up in that area is well beyond the scope of our study,” Galante said, later adding, “Our study is bigger than what the DOT asked for.”
Schulman called up Fishinger, who said that the allegations made by NASH’s consultants were all addressed and resolved in the updated plans submitted by Galante.
The plan “is not going to solve every existing problem on Main Avenue, it’s going to mitigate their traffic, and maybe then some,” Fishinger said.
The lights on Main Avenue need to be retimed and coordinated whether or not The Village is constructed, he said.
“The timings haven’t been updated in a while and that’s a big part of the problems you’re seeing out there, the lights just aren’t talking to each other,” Fishinger said.
“This isn’t the city’s last bit at the apple. The city will still be involved through the design process,” Fishinger said.
As “just a caution,” Fishinger called Galante’s predicted disaster with the five or six driveways a “worst case scenario.”
“Good planning and good design would expect you to interconnect the lots,” Fishinger said. “Traffic won’t be as bad as he predicts in that scenario.”
The cars that leave via the southern driveway can reenter the parking lot at the traffic light and turn around within if they want to head south, using the light to make the left turn, Fishinger said.
The applicant is responsible for retiming the lights on Main Avenue, but once it’s done the applicant’s responsibility is only for the intersection in front of the store, Fishinger said.
Assistant Planning and Zoning Director Mike Wrinn asked Fishinger if he thought the traffic situation on Main Avenue, with traffic lights that are not coordinated, is unusual.
“There is some system in place,” Fishinger said. “It’s antiquated. In a lot of cases the (detection) loops are present, it’s long since failed. The short answer is the state will get around to it eventually but the issue is they have got a lot on their plate, they just haven’t gotten to it. So, will they get to it? Eventually, I just don’t see it happening in the near future.”